Location: 37 Coastal Rd, East Preston, West Sussex
Project Date: March - April 2023
We were tasked by Cloud 9 with the demolition of an existing detached residential property located on a private estate. The project’s goal was to clear the site for a new build. The property, located in a desirable area of East Preston in West Sussex, required careful consideration of local regulations and community guidelines to ensure that the demolition was carried out smoothly and responsibly.
Challenges and Considerations
Given the location of the property on a private estate, the project faced several challenges related to local restrictions. These restrictions required close attention to detail, particularly in terms of waste management, noise control and working hours. The demolition work had to be conducted in a way that minimally impacted the surrounding community while also adhering to the estate’s policies. Additionally, ensuring proper site clearance to make way for redevelopment posed logistical challenges, as there was a need to protect the surrounding environment and infrastructure during the demolition process.
Outcome
We successfully completed the demolition of the existing property within the projected timeline. The site was thoroughly cleared, meeting all local regulations, and was prepared for the upcoming new build. Cloud 9 was pleased with the speed and efficiency of the work, which was completed without any significant disruption to the local area.
Environmental and Community Impact
The demolition project was carried out with a strong emphasis on environmental responsibility. All waste materials were carefully sorted for recycling, reducing the amount sent to landfill. The site was cleared in an eco-conscious manner, ensuring minimal impact on the surrounding environment. Furthermore, noise levels were kept to a minimum during the demolition process, respecting the private estate's noise regulations and ensuring no disturbance to the local community.
Key Features or Techniques
- Regulatory Compliance: Careful adherence to local estate restrictions and planning requirements.
- Waste Management: Implementation of an effective waste sorting system for recycling and reducing landfill impact.
- Efficient Site Clearance: Fast and effective site clearance, enabling the next phase of redevelopment to proceed smoothly.
Testimonials
“We are extremely satisfied with the demolition work completed by Rabbit Demolition. Their attention to detail and professionalism throughout the project ensured that we met all local requirements and stayed on schedule. The team worked within the estate’s restrictions, and we were impressed with how quickly the site was cleared and prepared for the new build. I would highly recommend their services for any similar projects.”